MECHANICAL
--Underground inspection: To be made after trenches or ditches are
excavated, underground duct and fuel piping installed, and
before any backfill is put in place.
--Rough-In inspection: To be made after the roof, framing, fire
blocking and bracing are in place and all ducting, and other
concealed components are complete, and prior to the installation
of wall or ceiling membranes.
--Final inspection: To be made after the building is complete, the
mechanical system is in place and properly connected, and the
structure is ready for occupancy.
GAS
--Rough piping inspection: To be made after all new piping
authorized by the permit has been installed, and before any such
piping has been covered or concealed or any fixtures or gas
appliances have been connected.
--Final piping inspection: To be made after all piping authorized
by the permit has been installed and after all portions which
are to be concealed by plastering or otherwise have been so
concealed, and before any fixtures or gas appliances have been
connected. This inspection shall include a pressure test.
--Final inspection: To be made on all new gas work authorized by
the permit and such portions of existing systems as may be
affected by new work or any changes, to insure compliance with
all the requirements of this code and to assure that the
installation and construction of the gas system is in accordance
with reviewed plans.
|